You can relate actual projects to a sequence using the following relation types:

You can change actual project dates by moving an actual project across the timeline. The Actual Project Sequence validation rule is executed while changing the related project dates. If dates in the project sequence violate the rule, the relation is highlighted in red.


To relate actual projects


  1. Select two actual projects.
  2. On the diagram toolbar, click Relate.
  3. Select one of the available relation types:


To remove the relation between actual projects


  1. Select two related actual projects.
  2. On the diagram toolbar, click Relate.
  3. Select None.


To resolve the incorrect actual project sequence


  1. On the highlighted relation shortcut menu, click Validate.
  2. Select one of the suggested solutions.

If you change dates of an actual project containing actual sub projects, actual sub project dates change correspondingly.