You can add a new or an existing actual project to the NPV-1 diagram.


To add a new actual project


  1. On the NPV-1 diagram toolbar, click Add New > Actual Project. On the diagram pane, an empty line for the newly created actual project appears.
  2. Specify a time frame for the actual project.


To add a new actual sub project


  1. Select the actual project for which you want to create an actual sub project.
  2. Do one of the following:
    • On the NPV-1 diagram toolbar, click Add New > Actual Sub Project.
    • On the shortcut menu of the selected actual project, click Add new Actual Sub Project.
  3. Specify a time frame for the actual sub project.


To add an existing actual project


  1. On the NPV-1 diagram toolbar, click Add Existing. The Select Element dialog opens.
  2. In the dialog, select an Actual project (or several actual projects) and click the + button.
  3. Click OK when you are done.