Abbreviation

COR2001

Message

Actual Project Milestone date exceeds Actual Project time period

Description

Actual Project Milestone date cannot exceed the Actual Project time period (start date - end date).

Severity

Error

Context element

Instance Specification

Solvers

You can select one of the following solvers:

  • Autocorrect - automatically fix Actual Project Milestone Date to Actual Projects start Date.
  • Edit Actual Project Milestone Date - the UPDM Time Dialog is opened where you can set the new Actual Project Milestone date.

Example

StartPhase milestone date changed to start date of project using Autocorrect solver

Activity

All
Personal filters
All