Abbreviation

COR2001

Message

Actual Project Milestone date exceeds Actual Project time period

Description

Actual Project Milestone date cannot exceed the Actual Project time period (start date - end date).

Severity

Error

Context element

Instance Specification

Solvers

You can select one of the following solvers:

  • Autocorrect - automatically fix Actual Project Milestone Date to Actual Projects start Date.
  • Edit Actual Project Milestone Date - the UPDM Time Dialog is opened where you can set the new Actual Project Milestone date.

Example

StartPhase milestone date changed to start date of project using Autocorrect solver