Message

Incorrect Milestone Dependency

Description

Actual Project Milestone Dates should correspond their sequence.

Severity

Error

Context element

Dependency

Solvers

You can use one of the following solvers:

  • Autocorrect - change Milestone Sequence Milestone To start date to be equal to Milestone From start date.
  • Edit From Milestone Date - open Date Dialog to edit Milestone From Actual Project Milestone date.
  • Edit To Milestone Date - open Date dialog to edit Milestone To Actual Project Milestone Date property.
  • Remove Milestone Dependency - remove Milestone Dependency.
  • Change Milestone Dependency Direction - change direction of the Milestone Dependency relationship.

Example

Changed Milestone date using Edit To Milestone Date solver