| id | 148925043 |
|---|
...
| id | 148925043 |
|---|
...
| id | 148925043 |
|---|
This section will describe how to use Activities in a BPMN process diagram. Activities (Tasks, Subprocesses, and Call Activities) can have the following specific markers displayed on their shapes:
- Compensation
- Standard loop
- MultiInstance loop (parallel)
- MultiInstance loop (sequential)
To add a Compensation marker to an Activity, do one of the following
...
- Right-click an Activity and
...
- select Is For Compensation.
- Open the Activity Specification window. Click to clear
...
- the Is For Compensation
...
- check box
...
- and click Close.
To add a Loop marker to an Activity
...
- Right-click an Activity and click to
...
- select Standard Loop
...
- or MultiInstance Loop.
To display a MultiInstance Loop (sequential) marker on a MultiInstance Loop activity, do one of the following
...
- Right-click an Activity with a MultiInstance Loop (parallel) marker and on the shortcut menu select Is Sequential.
- Open the Activity with a MultiInstance marker Specification window.
...
- Select Is Sequential
...
- and click Close.
To convert an Activity to another type of Activity
...
- Right-click a Task, SubProcess, or Call Activity and from the shortcut menu
...
- select Refactor
...
- > Convert To
...
- and then select an Activity type to which you need to convert the selected Activity.
To display Resources assigned for Activities
...
- Right-click the diagram pane and then do one of the following:
- On the shortcut menu, click to select
...
- the Show Assigned Resources
...
- check box (see the following figure).
- From the shortcut menu,
...
- select Diagram Properties
...
- and in the open dialog, set the Show Assigned Resources
...
- property value to true.
...
Related element
Related diagrams
Related procedures