You can add new or existing Resource Interactions to fill in an SV-6 table.

To add new Resource Interaction


  1. In the SV-6 diagram toolbar, click the Add New button. The Realized Resource Interaction wizard opens.
  2. Follow the steps of the wizard.
  3. Click Finish when you are done.
    The rows with created Resource Interactions are added to the table.

 

To add an existing Resource Interaction


  1. In the SV-6 diagram toolbar, click the Add Existing button. The Select Resource Interaction dialog opens.
  2. Select Resource Interactions by clicking + button.
  3. Click OK when you are done.
    The rows with selected Resource Interactions are added to the table.
  • Resource Interaction Identifier, Resource Interaction Item Name, Producing and Consuming Functions, and wide range of measurement cells are allowed to edit in the table.
  • Sending Resource, Receiving Resource, and Implements cells are read only.
  • You may use an SV-1 view to create or modify a Resource Interaction.
  • You can use Resource Interaction Manager dialog that enables to analyze and manage the Resource Interaction data.