The Technical and Environmental factors are associated with the weight of the project. You have to assign a value to each factor. The value assigned to a particular factor depends on the degree of influence a factor has. The relevance values range from 0 to 5, where 0 means no influence, 3 is the average level of influence, and 5 means a strong influence.
Technical Factors
The table below lists Technical Factors
| Factor | Technical Factors | Weight | Description | 
|---|---|---|---|
| T1 | Distributed  system  | 2.0 | The system distributed  architecture or centralized architecture.  | 
| T2 | Response  adjectives  | 1.0 | The response time is one  of the important criteria.  | 
| T3 | End-user  efficiency  | 1.0 | The end-user efficiency. | 
| T4 | Complex  processing  | 1.0 | The business process  is very complex.  | 
| T5 | Reusable  code  | 1.0 | The project maintains  high reusability. The design is complex.  | 
| T6 | Easy to  install  | 0.5 | The project requires  simple installation.  | 
| T7 | Easy to  use  | 0.5 | User-friendly is one of  the important criteria.  | 
| T8 | Portable | 2.0 | The project requires  cross-platform implementation.  | 
| T9 | Easy to  change  | 1.0 | The project is highly  customizable in the future. The architectural design is complex.  | 
| T10 | Concurrent | 1.0 | The project has a large  numbers of users working with locking support. The architecture increases the project complexity.  | 
| T11 | Security  features  | 1.0 | The project has heavy security. | 
| T12 | Access for  third parties  | 1.0 | The project is dependent on  the third party’s control. Studying and understanding the third party is required.  | 
| T13 | Special training  required  | 1.0 | The application is so complex  for the user that training must be provided.  | 
Use Case Driven Model Data E3.
Technical Factor Value
Technical Factor Value (TFactor) is obtained with the multiplication of the value of each Technical factor by its weight.
TFactor = value x weight
Technical Complexity Factor
Technical Complexity Factor (TCF) is obtained with the addition of 0.6 to the sum of TFactor multiplied by 0.01.
TCF = 0.6 + (0.01 * TFactor)
Environmental Factors
The Table below lists Environmental Factors
| Factor | Environmental Factors | Weight | Description | 
|---|---|---|---|
| E1 | Familiar  with RUP  | 1.5 | Staff in the project are familiar  with domain and technical details of the project.  | 
| E2 | Application  experience  | 0.5 | The application experience level. | 
| E3 | Object-oriented  experience  | 1.0 | Staff in the project have basic  knowledge of the OOP concept. The project is implemented on the object oriented design.  | 
| E4 | Lead analyst  capability  | 0.5 | The analyst who is leading the  project has enough domain knowledge.  | 
| E5 | Motivation | 1.0 | The project motivates staff to work  including how the software industry is going on.  | 
| E6 | Stable  requirements  | 2.0 | The requirements are clear,  stable, and unlikely to change in the future.  | 
| E7 | Part-time  workers  | -1.0 | Part-time staff are working on  the project.  | 
| E8 | Difficult  programming language  | -1.0 | Complexity of a programming  language.  | 
Use Case Driven Model Data E3.
Environmental Factor Value
Environmental Factor Value (EFactor) is obtained with the multiplication of the value of each Environmental factor by its weight.
Environmental Factor
Environmental Factor (EF) is obtained with the addition of 1.4 to the sum of EFactor multiplied by -0.03.
EF = 1.4 + (-0.03 * EFactor)
Project Estimation
Variables of Use Case Project Estimation.
Adjusted Use Case Points
The Adjusted Use Case Point (UCP) is determined with the multiplication of Unadjusted Use Case Point (UUCP) by Technical Complexity Factor (TCF) and Environmental Factor (EF).
UCP = UUCP * TCF * EF
Estimated Effort in Person Hours
The person hours multiplier or X hours is a ratio of the number of man hours (PHM) per Use Case Point based on past projects. If no historical data has been collected, industry experts suggest using a figure between 15 and 30. A typical value is 20.
X hours = UCP * PHM
Estimated Effort in Scheduled Time
Divide X hours by the number of developers working on the project and working hours per day to determine Estimated Effort in Scheduled Time or Y days. This means that with nDev developers, it would take Y days to complete the project.
Y days = X / nDev / hay
Estimated Effort in Working Days
Divide Y days by working days per month to get the estimated effort in working days or Z months. This means that with nDev developers, it would take Z month to complete the project.
Z months = Y / d Month