Abbreviation
COR2005
Message
Order of Actual Project dates is incorrect in a project sequence
Description
Actual Project Dates should correspond to their sequence.
Severity
Error
Context element
Dependency
Solvers
You can use one of the following solvers:
- Autocorrect - change Project Sequence Project To start Date to be equal to Project From start Date.
- Edit From Project Start Date - open Date Dialog to specify Project Milestone's Project From Start Date.
- Edit To Project Start Date - open Date Dialog to specify Project Sequences Project To Start Date.
- Remove Project Sequence - remove Project Sequence from Model.
- Change Project Sequence Direction - change Direction of Project Sequence.
Example