On this page
Creating StV-5 table
The content of the StV-5 table are Resources used by Actual Organizational Resources (Actual Organizations and Actual Posts) to realize Capabilities in a particular time period. Rows of the StV-5 table are Actual Organizational Resources, and columns are Capabilities.
A relationship between an Actual Organizational Resource and a Resource is expressed by the Actual Project Milestone. There can be one or more Resources related to the Actual Organizational Resource.
A StV-5 table can be owned by an Enterprise Phase that will be the context element for this table. The Enterprise Phases are modeled in the StV-1 view.
A relationship between a Capability and a context element is represented by the Exhibits.
To add rows to a StV-5 table
- 1. Click the Add Rows button in the table toolbar or press Ctrl+Insert. The element Selection dialog will open.
- 2. Select Actual Organizational Resources you need to add to the table. For the detailed information about the element Selection dialog see Selecting elements.
- 3. Click OK when you are finished.
To add resources to a StV-5 table
- Click the cell wherein you want to add a resource.
- Click the + button that will appear at the right of the selected cell. The Deployment Milestones wizard will open.
- Using the Deployment Milestones wizard select resources and specify both deployment and no longer used dates for them.
- Click Finish when you are done.
Modifying StV-5 table
Please refer to Managing tables, if you are looking for the following table handling features:
- Delete the selected row.
- Delete the selected row from the table.
- Move the selected row up.
- Move the selected row down.
- Export a table to a plain text file format (.cvs) or a Hypertext Markup Language format (.html).
- Generate a report.
To add/ remove columns to a StV-5 table
- In the table toolbar, click the Add/ Remove Columns button. The element Selection dialog will open.
- Select capabilities to add or remove from a table. For the detailed information about the element Selection dialog see Selecting elements.
Click OK when you are finished.
- Capabilities will be removed only from the table. They will not be removed from the model.
- An Exhibits relationship between the context element and a removed Capability will be removed from the model.
- An Exhibits relationship between the context element and an added Capability will be added in the model.
To add/ remove resources to a StV-5 table
- Click the cell you want to edit.
- The + and - buttons will appear at the right of the cell.
- Do one of the following:
- Click the + button to add a resource. The Deployment Milestones wizard will open.
- Select a resource you want to remove and click the - button.