Abbreviation

COR2005

Message

Order of Actual Project dates is incorrect in a project sequence

Description

Actual Project Dates should correspond to their sequence.

Severity

Error

Context element

Dependency

Solvers

You can use one of the following solvers:

  • Autocorrect - change Project Sequence Project To start Date to be equal to Project From start Date.
  • Edit From Project Start Date - open Date Dialog to specify Project Milestone's Project From Start Date.
  • Edit To Project Start Date - open Date Dialog to specify Project Sequences Project To Start Date.
  • Remove Project Sequence - remove Project Sequence from Model.
  • Change Project Sequence Direction - change Direction of Project Sequence.

Example

Changed Project dates using Edit To Project Start Date solver